Mamuju, Sulbarkita.com -- The Directorate General of Human Settlements of the Ministry of Public Works ensured that the University of West Sulawesi (Unsulbar) campus which was stalled in the Padha-Padhang Environment, East Banggae District, Majene, would continue construction in 2020.
"The focus of development is buildings 1 and 2 which have been stalled," said Staff Commitment Officer (PPK) Directorate General of Human Settlements, Kikit, to Sulbarkita.com via telephone, Friday, December 20, 2019.
Secretary of the North West Sulawesi Construction Services Implementation Implementing Agency Secretary Andi Ika Wahyuni said the budget for the project was Rp 60 billion. The budget comes from the central government.
"I don't know the details of the budget post but about 60 billion rupiah," Andi Ika said in his office, Jalan Maccirinnae, Binanga Village, Mamuju District, Thursday, December 19, 2019.
Thus the amount of the budget is not as big as what was revealed by the Chancellor Unsulbar Akhsan Djalaluddin, which is Rp. 70 billion. "With this budget, we hope that the construction of stalled buildings can be accelerated," Akhsan said, as quoted by karakterunsulbar.com, Monday 4 November 2019.
The Unsulbar building in Padha-Padhang which was built in 2016 was stalled. Most of the room is not functioning because it is still half-finished. As a result, the Unsulbar rector borrowed a number of office buildings to become lectures.
Head of Planning Section, Directorate General of Human Settlements, Abdul Rahman, said the stalled building occurred when the Unsulbar himself managed the project. To prevent similar conditions from occurring, the Directorate General of Human Settlements intervened. "We are now taking over the construction," he told Sulbarkita.com in his office, Jalan Abdul Malik Pattana Endeng, Binanga Village, Simboro District, Friday, December 20, 2019.
According to Rahman the hall was in the process of auctioning the project. Unfortunately the auction process, Andi Ika continued, failed on schedule last week. "The status of the tender failed because all the companies that registered did not meet the criteria," Andi said while saying he would re-open the auction again in the near future.